Worked example · Hydrology

Commercial parcel runoff after pavement removal

A drainage retrofit removes pavement in part of a commercial parcel and restores landscaped cover. Keep the parcel boundary fixed.

Inputs

Drainage zones
ZoneArea (acre)Pre CNPost CN
Zone 1
0–5,000 acre
30–98
30–98
Zone 2
0–5,000 acre
30–98
30–98
Zone 3
0–5,000 acre
30–98
30–98

Keep each zone footprint the same across both conditions. Subdivide cover where needed and use zero area for unused zones.

Rainfall event
0–60 in

Match the curve numbers to the selected abstraction convention.

Rainfall partition

Live results
Rainfall partition Post-development runoff decreases. The volume change is post-development minus pre-development. POST RUNOFF 3.13 in PRE RUNOFF 4.28 in VOLUME CHANGE -0.535 acre-ft POST CN 82.5 Event rain5 in4.28 inExisting3.13 inDeveloped 0% · retainedPost runoff share100% · runoff

Post-development runoff decreases

The volume change is post-development minus pre-development.

Calculation results

Post runoff
3.13 in
Pre runoff
4.28 in
Volume change
-0.535 acre-ft
Post CN
82.5
Pre-development CN
93.7
Drainage area
5.6 acre
Pre retention
0.67 in
Post retention
2.12 in
Pre initial abstraction
0.13 in
Post initial abstraction
0.42 in
Pre runoff volume
1.996 acre-ft
Post runoff volume
1.461 acre-ft
Runoff depth change
-1.15 in

Worked calculation

At the same 5 in storm, the chart shows the shift from runoff to retained rainfall. Compare the volume saved with the irrigated area of the retrofit.

S = 1000/CN − 10 (inches) · Iₐ = λS · Qd = (P − Iₐ)²/(P − Iₐ + S) for P > Iₐ, else 0.

The 0.20 option follows TR-55. The 0.05 option evaluates the entered CN values as supplied. For design with 0.05, use curve numbers calibrated to that choice. Weighted CN is evaluated before the nonlinear runoff equation. For strongly mixed or hydraulically disconnected cover, consider separate runoff calculations.

Open the main calculator