Worked example · Hydrology
Commercial parcel runoff after pavement removal
A drainage retrofit removes pavement in part of a commercial parcel and restores landscaped cover. Keep the parcel boundary fixed.
Inputs
Rainfall partition
Live resultsPost-development runoff decreases
The volume change is post-development minus pre-development.
Calculation results
- Post runoff
- 3.13 in
- Pre runoff
- 4.28 in
- Volume change
- -0.535 acre-ft
- Post CN
- 82.5
- Pre-development CN
- 93.7
- Drainage area
- 5.6 acre
- Pre retention
- 0.67 in
- Post retention
- 2.12 in
- Pre initial abstraction
- 0.13 in
- Post initial abstraction
- 0.42 in
- Pre runoff volume
- 1.996 acre-ft
- Post runoff volume
- 1.461 acre-ft
- Runoff depth change
- -1.15 in
Worked calculation
At the same 5 in storm, the chart shows the shift from runoff to retained rainfall. Compare the volume saved with the irrigated area of the retrofit.
S = 1000/CN − 10 (inches) · Iₐ = λS · Qd = (P − Iₐ)²/(P − Iₐ + S) for P > Iₐ, else 0.
The 0.20 option follows TR-55. The 0.05 option evaluates the entered CN values as supplied. For design with 0.05, use curve numbers calibrated to that choice. Weighted CN is evaluated before the nonlinear runoff equation. For strongly mixed or hydraulically disconnected cover, consider separate runoff calculations.
More worked examples
Open the main calculatorCommercial parcel runoff after pavement removal
Inputs
- Zone 1 area
- 3.2 acre
- Zone 1 pre-development CN
- 98
- Zone 1 post-development CN
- 88
- Zone 2 area
- 1.8 acre
- Zone 2 pre-development CN
- 91
- Zone 2 post-development CN
- 74
- Zone 3 area
- 0.6 acre
- Zone 3 pre-development CN
- 79
- Zone 3 post-development CN
- 79
- Event rainfall
- 5 in
- Initial abstraction
- 0.20 S · TR-55
Results
- Post runoff
- 3.13 in
- Pre runoff
- 4.28 in
- Volume change
- -0.535 acre-ft
- Post CN
- 82.5
- Pre-development CN
- 93.7
- Drainage area
- 5.6 acre
- Pre retention
- 0.67 in
- Post retention
- 2.12 in
- Pre initial abstraction
- 0.13 in
- Post initial abstraction
- 0.42 in
- Pre runoff volume
- 1.996 acre-ft
- Post runoff volume
- 1.461 acre-ft
- Runoff depth change
- -1.15 in
Post-development runoff decreases
The volume change is post-development minus pre-development.
S = 1000/CN − 10 (inches) · Iₐ = λS · Qd = (P − Iₐ)²/(P − Iₐ + S) for P > Iₐ, else 0.
Screening worksheet · Verify design using project criteria and site data.