Worked example · Concrete quantities

12×20 × 4-Inch Concrete Patio with 80 lb Bags

The patio measures 12 ft by 20 ft inside the forms. A uniform 4 in. slab and 10% allowance provide a basis for comparing bagged concrete and ready mix.

Example inputs

Pour scope
Slab dimensions
ft
ft
in
Material allowances
%
#4 rebar grid
in
in
ft
in
See results

Worked result

Updates as you type
Concrete before waste
2.963 yd³
Concrete to order
3.259 yd³
80 lb bags to order
147

Slab and pier section

Schematic
Slab and pier section 20 ft12 ftSlab · 4 in thick#4 grid up to 18 in OC

Calculation details

Concrete before waste
2.963 yd³
Concrete to order
3.259 yd³
80 lb bags to order
147
Slab volume
2.963 yd³
Volume per pier
0 ft³
40 lb bags
294
60 lb bags
196
80 lb bags
147
#4 cut pieces including laps
24
#4 rebar length including laps
352 ft
Lengthwise bar lines
9
Crosswise bar lines
15

Checks and references

  • Within limit
    Slab thickness reference

    R506.1 uses 3½ in. as a minimum for concrete floors on ground where that section applies. Confirm the detail for the actual slab use.

  • Reference
    Rebar detailing

    The grid is a quantity model. Confirm bar cover, laps, support, joints and reinforcement with the approved slab detail.

Worked calculation

The steps use US customary units for the reference formulas.

  1. Find slab volume

    20 × 12 ft × 4/12 ft = 80 ft³.

  2. Order bags or ready mix

    Apply 10% waste to 80 ft³. Divide by 0.30, 0.45 or 0.60 ft³ per bag and round up. With 80 lb bags, order 147 bags.

  3. Count the rebar grid

    9 runs of 19.67 ft and 15 runs of 11.67 ft. Break long runs across 20 ft stock with 24 in. laps for 24 pieces and 352 ft total.

Frequently asked questions

How many 80 lb bags cover a 12×20 patio at 4 inches thick?

With 10% waste and a 0.60 ft³ yield, the 88 ft³ order volume takes 147 bags.

What ready-mix quantity equals the 12×20 slab estimate?

The net volume is about 2.96 yd³. The 10% order allowance increases it to about 3.26 yd³.