Worked example · Concrete quantities

8×12 Slab and Three 14-Inch Piers in One Pour

The flat equipment pad is 8×12 ft and 4 in. thick. Three separate 14 in. piers use a 30 in. cylinder depth and carry 750 lb each.

Example inputs

Pour scope
Slab dimensions
ft
ft
in
Cylindrical piers
in
in
lb
Material allowances
%
#4 rebar grid
in
in
ft
in
See results

Worked result

Updates as you type
Concrete before waste
1.482 yd³
Concrete to order
1.66 yd³
80 lb bags to order
75

Slab and pier section

Schematic
Slab and pier section 12 ft8 ftSlab · 4 in thick#4 grid up to 18 in OC14 in30 in3 cylindrical piersGross bearing 1,076.6 psf

Calculation details

Concrete before waste
1.482 yd³
Concrete to order
1.66 yd³
80 lb bags to order
75
Slab volume
1.185 yd³
Volume per pier
2.67 ft³
40 lb bags
150
60 lb bags
100
80 lb bags
75
Bearing pressure per pier
1,077 psf
#4 cut pieces including laps
16
#4 rebar length including laps
150.67 ft
Lengthwise bar lines
7
Crosswise bar lines
9

Checks and references

  • Within limit
    Slab thickness reference

    R506.1 uses 3½ in. as a minimum for concrete floors on ground where that section applies. Confirm the detail for the actual slab use.

  • Within limit
    Soil bearing

    The axial load plus concrete self-weight produces 1,077 psf against 1,500 psf entered capacity.

  • Reference
    Rebar detailing

    The grid is a quantity model. Confirm bar cover, laps, support, joints and reinforcement with the approved slab detail.

Worked calculation

The steps use US customary units for the reference formulas.

  1. Find slab volume

    12 × 8 ft × 4/12 ft = 32 ft³.

  2. Add the cylindrical piers

    π × (14/24)² ft² × 30/12 ft = 2.67 ft³ per pier. Multiply by 3. Gross base pressure is 1,077 psf per pier.

  3. Order bags or ready mix

    Apply 12% waste to 40.02 ft³. Divide by 0.30, 0.45 or 0.60 ft³ per bag and round up. With 80 lb bags, order 75 bags.

  4. Count the rebar grid

    7 runs of 11.67 ft and 9 runs of 7.67 ft. Break long runs across 20 ft stock with 24 in. laps for 16 pieces and 150.67 ft total.

Frequently asked questions

How should the slab and pier volumes be added for a shared concrete order?

Calculate the 32 ft³ slab plus three cylinder volumes, then apply the entered 12% allowance to the total.

Does the combined concrete order use slab weight in each pier bearing calculation?

The pier calculation uses the entered load from above plus each pier’s own concrete. Include transferred slab weight in the load input when the structural detail sends it to the pier.

Other calculators