Worked example · Concrete quantities
8×12 Slab and Three 14-Inch Piers in One Pour
The flat equipment pad is 8×12 ft and 4 in. thick. Three separate 14 in. piers use a 30 in. cylinder depth and carry 750 lb each.
Example inputs
Worked result
Updates as you type- Concrete before waste
- 1.482 yd³
- Concrete to order
- 1.66 yd³
- 80 lb bags to order
- 75
Slab and pier section
SchematicProject inputs
- Concrete to calculate
- Slab and piers
- Slab length
- 12 ft
- Slab width
- 8 ft
- Slab thickness
- 4 in
- Number of piers
- 3
- Pier base diameter
- 14 in
- Concrete depth per pier
- 30 in
- Service load on each pier
- 750 lb
- Allowable soil bearing
- 1,500 psf
- Concrete waste allowance
- 12%
- Bag product weight
- 80 lb bag
- Grid estimate
- Include
- Maximum bar spacing
- 18 in
- Clear side cover
- 2 in
- Stock bar length
- 20 ft
- Entered lap per splice
- 24 in
Calculation details
- Concrete before waste
- 1.482 yd³
- Concrete to order
- 1.66 yd³
- 80 lb bags to order
- 75
- Slab volume
- 1.185 yd³
- Volume per pier
- 2.67 ft³
- 40 lb bags
- 150
- 60 lb bags
- 100
- 80 lb bags
- 75
- Bearing pressure per pier
- 1,077 psf
- #4 cut pieces including laps
- 16
- #4 rebar length including laps
- 150.67 ft
- Lengthwise bar lines
- 7
- Crosswise bar lines
- 9
Checks and references
- Within limit
Slab thickness reference
R506.1 uses 3½ in. as a minimum for concrete floors on ground where that section applies. Confirm the detail for the actual slab use.
- Within limit
Soil bearing
The axial load plus concrete self-weight produces 1,077 psf against 1,500 psf entered capacity.
- Reference
Rebar detailing
The grid is a quantity model. Confirm bar cover, laps, support, joints and reinforcement with the approved slab detail.
Worked calculation
The steps use US customary units for the reference formulas.
Find slab volume
12 × 8 ft × 4/12 ft = 32 ft³.
Add the cylindrical piers
π × (14/24)² ft² × 30/12 ft = 2.67 ft³ per pier. Multiply by 3. Gross base pressure is 1,077 psf per pier.
Order bags or ready mix
Apply 12% waste to 40.02 ft³. Divide by 0.30, 0.45 or 0.60 ft³ per bag and round up. With 80 lb bags, order 75 bags.
Count the rebar grid
7 runs of 11.67 ft and 9 runs of 7.67 ft. Break long runs across 20 ft stock with 24 in. laps for 16 pieces and 150.67 ft total.
Enter valid values to see the steps for this layout.
Frequently asked questions
How should the slab and pier volumes be added for a shared concrete order?
Calculate the 32 ft³ slab plus three cylinder volumes, then apply the entered 12% allowance to the total.
Does the combined concrete order use slab weight in each pier bearing calculation?
The pier calculation uses the entered load from above plus each pier’s own concrete. Include transferred slab weight in the load input when the structural detail sends it to the pier.