Worked example · Concrete quantities
20×24 × 5-Inch Garage Slab Concrete Yardage
A rectangular garage floor has 20×24 ft inside-form dimensions and a 5 in. field thickness. Start with the flat slab volume so thickened edges can be measured separately.
Example inputs
Worked result
Updates as you type- Concrete before waste
- 7.407 yd³
- Concrete to order
- 8.148 yd³
- 80 lb bags to order
- 367
Slab and pier section
SchematicProject inputs
- Concrete to calculate
- Slab only
- Slab length
- 24 ft
- Slab width
- 20 ft
- Slab thickness
- 5 in
- Concrete waste allowance
- 10%
- Bag product weight
- 80 lb bag
- Grid estimate
- Include
- Maximum bar spacing
- 16 in
- Clear side cover
- 2 in
- Stock bar length
- 20 ft
- Entered lap per splice
- 24 in
Calculation details
- Concrete before waste
- 7.407 yd³
- Concrete to order
- 8.148 yd³
- 80 lb bags to order
- 367
- Slab volume
- 7.407 yd³
- Volume per pier
- 0 ft³
- 40 lb bags
- 734
- 60 lb bags
- 489
- 80 lb bags
- 367
- #4 cut pieces including laps
- 51
- #4 rebar length including laps
- 784.33 ft
- Lengthwise bar lines
- 16
- Crosswise bar lines
- 19
Checks and references
- Within limit
Slab thickness reference
R506.1 uses 3½ in. as a minimum for concrete floors on ground where that section applies. Confirm the detail for the actual slab use.
- Reference
Rebar detailing
The grid is a quantity model. Confirm bar cover, laps, support, joints and reinforcement with the approved slab detail.
Worked calculation
The steps use US customary units for the reference formulas.
Find slab volume
24 × 20 ft × 5/12 ft = 200 ft³.
Order bags or ready mix
Apply 10% waste to 200 ft³. Divide by 0.30, 0.45 or 0.60 ft³ per bag and round up. With 80 lb bags, order 367 bags.
Count the rebar grid
16 runs of 23.67 ft and 19 runs of 19.67 ft. Break long runs across 20 ft stock with 24 in. laps for 51 pieces and 784.33 ft total.
Enter valid values to see the steps for this layout.
Frequently asked questions
How many cubic yards are in the flat field of a 20×24 garage slab at 5 inches?
The 200 ft³ field equals about 7.41 yd³. At 10% waste the modeled order is about 8.15 yd³.
How do thickened garage slab edges change the takeoff?
Measure the extra cross-sectional area below the flat slab, multiply by edge length and allow for overlaps at corners.