Single PEX Loop at the 300 ft Planning Limit

A 224 ft² addition uses 12-inch spacing and a 38 ft one-way lead. With no added layout allowance, active tubing and the two leads just fit the half-inch loop cap.

Try it Add a small layout allowance or increase the one-way lead by a foot. The loop count should rise because the original design has no spare length.

Floor and circuit geometry
ft²
ft

Supply and return leads both count toward the loop limit.

%

Add a margin for bends and irregular coverage if required.

Hydronic load
Btu/(h·ft²)
°F
Balanced loops / port pairs
1
Total PEX tubing
300 ft
Zone water flow
0.72 US gal/min

The loop count balances equal areas. Check pressure drop, actual routes and the floor’s heat output before selection.

Serpentine loop sketch

Serpentine PEX circuit layout1 balanced loops at 300 ft each. Maximum planned length 300 ft. 12 in on center1 loopSupply / return manifold300 ft and 0.72 US gal/min per loop
The sketch represents equal-area circuits and paired leads. Use a scaled plan for route placement and bend geometry.
Length per loop with leads
300 ft
Planning limit per loop
300 ft
Active tubing across floor
224 ft
Supply + return lead per loop
76 ft
Water flow per loop
0.72 US gal/min
Total zone heat load
3,584 Btu/h
Download

How this calculation works

Active tubing length is net area ÷ spacing, plus the entered allowance. Add two times the one-way lead to every circuit. Divide active length by the usable length per loop and round up.

Each circuit serves an equal share of the area in this estimate. One supply-and-return port pair is needed per circuit. The planning limits are 300 ft for ½-in PEX and 400 ft for ⅝-in PEX, including leads.

Total water flow in US gallons per minute is load in Btu/h divided by 500.4 times the supply-to-return temperature drop in °F. Glycol concentration, operating temperature, pressure drop, floor output, bend radius and pump selection require project-specific checks.

References

Frequently asked questions

Why does increasing this lead by one foot add a circuit?

The original loop uses exactly 300 ft. Adding a foot each way would need 302 ft, so it crosses the entered planning cap.

Should I order exactly 300 ft for the addition?

Use the plan and manufacturer requirements to check bend geometry, actual routing and spare length. The example leaves no allowance for field changes.