A 90 ft² Tile Mudroom with One PEX Circuit

A 90 ft² mudroom uses 6-inch spacing to screen a high load near an exterior door. The manifold is about 20 ft away, and the installer includes a 5% active length allowance.

Try it Change the water temperature drop from 10°F to 15°F. The flow target changes while the layout length stays the same.

Floor and circuit geometry
ft²
ft

Supply and return leads both count toward the loop limit.

%

Add a margin for bends and irregular coverage if required.

Hydronic load
Btu/(h·ft²)
°F
Balanced loops / port pairs
1
Total PEX tubing
229 ft
Zone water flow
0.54 US gal/min

The loop count balances equal areas. Check pressure drop, actual routes and the floor’s heat output before selection.

Serpentine loop sketch

Serpentine PEX circuit layout1 balanced loops at 229 ft each. Maximum planned length 300 ft. 6 in on center1 loopSupply / return manifold229 ft and 0.54 US gal/min per loop
The sketch represents equal-area circuits and paired leads. Use a scaled plan for route placement and bend geometry.
Length per loop with leads
229 ft
Planning limit per loop
300 ft
Active tubing across floor
189 ft
Supply + return lead per loop
40 ft
Water flow per loop
0.54 US gal/min
Total zone heat load
2,700 Btu/h
Download

How this calculation works

Active tubing length is net area ÷ spacing, plus the entered allowance. Add two times the one-way lead to every circuit. Divide active length by the usable length per loop and round up.

Each circuit serves an equal share of the area in this estimate. One supply-and-return port pair is needed per circuit. The planning limits are 300 ft for ½-in PEX and 400 ft for ⅝-in PEX, including leads.

Total water flow in US gallons per minute is load in Btu/h divided by 500.4 times the supply-to-return temperature drop in °F. Glycol concentration, operating temperature, pressure drop, floor output, bend radius and pump selection require project-specific checks.

References

Frequently asked questions

What part of the mudroom tubing estimate is outside the room?

The two 20 ft manifold leads contribute 40 ft to total length. The remaining estimated 189 ft covers the floor and the layout allowance.

Why should floor surface temperature be checked in the tiled mudroom?

The heat flux input describes room demand. The floor finish, tube depth, water temperature and comfort limits determine how much heat the assembly delivers.