Excavation Cut & Fill, Soil Swell and Shrinkage Calculator
Calculate tapered trench or pit excavation, bank, loose and compacted volume, truck trips and fill balance.
Estimate
- Use site-specific swell and shrink factors. Excavation protection and payload limits require a separate site review.
- Loose excavation · LCY
- 127.315 yd³
- Available compacted fill · CCY
- 89.63 yd³
- Loose-volume truck trips
- 11
- Top opening width
- 8 ft
- Top opening length
- 100 ft
- Compacted surplus or deficit
- 49.63 yd³
- Bank borrow needed
- 0 yd³
Download
How the estimate works
Measure the excavation in place
A trench uses a constant trapezoidal cross-section with square ends. A pit grows in both directions and uses the bottom, midpoint and top areas in the prismoidal formula.
Track each material state
Loose volume equals bank volume × (1 + swell). Available compacted volume equals bank volume × (1 − shrink). Both percentages use the bank state as the reference.
Compare fill and hauling
Compare available compacted material to compacted fill demand. Truck trips use loose volume and the entered usable capacity. Confirm payload and suitable material separately.
References
Questions & answers
What is the difference between BCY, LCY and CCY?
Bank cubic yards measure soil in place. Loose cubic yards measure it after excavation. Compacted cubic yards measure the placed fill.
Can the bank-to-compacted shrink percentage be negative?
Yes. A negative number models compacted bulking relative to the bank condition, which can occur with excavated rock. Use the project geotechnical factors.
Does the pit volume account for battered ends?
The pit model assumes equal batter on all four sides. The trench model uses battered long sides and square ends.