Worked example

Square-side trench quantity from a shored detail

The volume takeoff uses the vertical geometry shown on a site-specific shoring detail, over a 72 ft trench with a 4.5 ft bottom.

Inputs

Measurement system
ft
ft
ft
H:1V
Horizontal run for one unit of vertical rise. Volume geometry only.
%
%
Negative shrink represents compacted expansion relative to bank.
yd³
yd³
TRENCH SECTION & MATERIAL STATESBattered excavation cross section and bank, loose and compacted volumes. TRENCH SECTION & MATERIAL STATES 4.5 ft4.5 ftDepth 7 ftBANK84 yd³LOOSE110.88 yd³COMPACTED74.76 yd³

Estimate

Bank excavation · BCY
84 yd³
  • Use site-specific swell and shrink factors. Excavation protection and payload limits require a separate site review.
Loose excavation · LCY
110.88 yd³
Available compacted fill · CCY
74.76 yd³
Loose-volume truck trips
11
Top opening width
4.5 ft
Top opening length
72 ft
Compacted surplus or deficit
20.76 yd³
Bank borrow needed
0 yd³
Download

Working this example

Starting estimate 84 yd³Bank excavation · BCY

Confirm net excavation width against the actual shoring envelope and installation sequence.

See the calculator formulas and assumptions

Questions & answers

What volume formula does zero batter give for this shored trench?

The section reduces to a rectangle. 72 × 4.5 × 7 gives 2,268 ft³, or 84 BCY.

Is a zero-batter input a shoring selection for the trench?

It describes the volume geometry. The actual protective system depends on the approved site-specific plan.