Worked example

Metric sand and gravel drainage trench

A drainage trench is 85 m long with a 650 mm bottom and 1.5 m depth. Its preliminary takeoff uses sand and gravel factors and 8 m³ usable truck volume.

Inputs

Measurement system
m
m
m
H:1V
Horizontal run for one unit of vertical rise. Volume geometry only.
%
%
Negative shrink represents compacted expansion relative to bank.
m³
m³
TRENCH SECTION & MATERIAL STATESBattered excavation cross section and bank, loose and compacted volumes. TRENCH SECTION & MATERIAL STATES 1.55 m0.65 mDepth 1.5 mBANK140.25 m³LOOSE161.29 m³COMPACTED131.84 m³

Estimate

Bank excavation · BCM
140.25 m³
  • Use site-specific swell and shrink factors. Excavation protection and payload limits require a separate site review.
Loose excavation · LCM
161.288 m³
Available compacted fill · CCM
131.835 m³
Loose-volume truck trips
21
Top opening width
1.55 m
Top opening length
85 m
Compacted surplus or deficit
76.835 m³
Bank borrow needed
0 m³
Download

Working this example

Starting estimate 140.25 m³Bank excavation · BCM

Run separate quantities for granular bedding, excavated spoil and imported fill when different material requirements apply.

See the calculator formulas and assumptions

Questions & answers

How wide is the top of the metric drainage trench?

The batter adds 0.30 × 1.5 = 0.45 m on each side. The top width is 1.55 m.

Should the truck capacity use loose or compacted cubic meters for this trench?

Use the usable loose volume per truck and confirm allowable mass for the soil moisture and material.