Worked example

Rock excavation with compacted bulking

A rock excavation has a 20 × 16 ft bottom. The takeoff carries 55% bank-to-loose swell and negative 20% shrink for placed rock fill.

Inputs

Measurement system
ft
ft
ft
H:1V
Horizontal run for one unit of vertical rise. Volume geometry only.
%
%
Negative shrink represents compacted expansion relative to bank.
yd³
yd³
PIT SECTION & MATERIAL STATESBattered excavation cross section and bank, loose and compacted volumes. PIT SECTION & MATERIAL STATES 17.8 ft16 ftDepth 6 ftBANK78.55 yd³LOOSE121.75 yd³COMPACTED94.26 yd³

Estimate

Bank excavation · BCY
78.551 yd³
  • Use site-specific swell and shrink factors. Excavation protection and payload limits require a separate site review.
Loose excavation · LCY
121.754 yd³
Available compacted fill · CCY
94.261 yd³
Loose-volume truck trips
13
Top opening width
17.8 ft
Top opening length
21.8 ft
Compacted surplus or deficit
19.261 yd³
Bank borrow needed
0 yd³
Download

Working this example

Starting estimate 78.551 yd³Bank excavation · BCY

Check fragmentation, voids, placement suitability and weight-limited payload before relying on modeled rock quantities.

See the calculator formulas and assumptions

Questions & answers

What does negative 20% shrink do to the compacted rock volume?

It makes the compacted estimate 1.20 times bank volume, reflecting bulking relative to intact rock.

Why might rock haul trips exceed the volume-based count here?

Dense or large pieces can hit legal payload or usable loading limits before the nominal truck body is full.