A basement excavation has a 44 × 30 ft bottom including working space. The pit model expands both top dimensions with a 0.75H:1V geometry input.

Inputs

Measurement system
ft
ft
ft
H:1V
Horizontal run for one unit of vertical rise. Volume geometry only.
%
%
Negative shrink represents compacted expansion relative to bank.
yd³
yd³
PIT SECTION & MATERIAL STATESBattered excavation cross section and bank, loose and compacted volumes. PIT SECTION & MATERIAL STATES 43.5 ft30 ftDepth 9 ftBANK626.75 yd³LOOSE846.11 yd³COMPACTED564.08 yd³

Estimate

Bank excavation · BCY
626.75 yd³
  • Use site-specific swell and shrink factors. Excavation protection and payload limits require a separate site review.
Loose excavation · LCY
846.113 yd³
Available compacted fill · CCY
564.075 yd³
Loose-volume truck trips
57
Top opening width
43.5 ft
Top opening length
57.5 ft
Compacted surplus or deficit
424.075 yd³
Bank borrow needed
0 yd³
Download

Working this example

Starting estimate 626.75 yd³Bank excavation · BCY

Use the working excavation footprint, which includes room for the construction detail and access requirements.

See the calculator formulas and assumptions

Questions & answers

What is the top opening of this battered basement pit?

Each side grows 0.75 × 9 = 6.75 ft from bottom to top. The opening is 57.5 × 43.5 ft.

Why use a midpoint area for the clay basement pit?

Both plan dimensions change with depth, so plan area changes quadratically. The prismoidal formula accounts for that curvature.