Worked example
Haul estimate for a metric chamber pit
The storm chamber installation has a 19 × 11 m bottom footprint and excavation depth of 2.8 m. A custom allowance adjusts the loam preset.
Estimate
Bank excavation · BCM
- Use site-specific swell and shrink factors. Excavation protection and payload limits require a separate site review.
- Loose excavation · LCM
- 945.562 m³
- Available compacted fill · CCM
- 645.384 m³
- Loose-volume truck trips
- 95
- Top opening width
- 14.64 m
- Top opening length
- 22.64 m
- Compacted surplus or deficit
- 480.384 m³
- Bank borrow needed
- 0 m³
Download
Working this example
Starting estimate 750.446 m³Bank excavation · BCM
Compare the cut to the installed chamber and stone volume. Only suitable soil can be credited toward the compacted fill target.
Questions & answers
How do I include a sloping access ramp for this chamber excavation?
Measure ramp excavation beyond the pit as a separate prismoid or as surveyed end areas.
Does changing the chamber pit’s target fill change spoil truck trips?
The truck estimate assumes all loose cut is hauled. A net export plan must subtract the usable soil kept on site.