ConcreteEarthLab

Worked example

Haul estimate for a metric chamber pit

The storm chamber installation has a 19 × 11 m bottom footprint and excavation depth of 2.8 m. A custom allowance adjusts the loam preset.

Inputs

Measurement system
m
m
m
H:1V
Horizontal run for one unit of vertical rise. Volume geometry only.
%
%
Negative shrink represents compacted expansion relative to bank.
m³
m³
PIT SECTION & MATERIAL STATESBattered excavation cross section and bank, loose and compacted volumes. PIT SECTION & MATERIAL STATES 14.64 m11 mDepth 2.8 mBANK750.45 m³LOOSE945.56 m³COMPACTED645.38 m³

Estimate

Bank excavation · BCM
750.446 m³
  • Use site-specific swell and shrink factors. Excavation protection and payload limits require a separate site review.
Loose excavation · LCM
945.562 m³
Available compacted fill · CCM
645.384 m³
Loose-volume truck trips
95
Top opening width
14.64 m
Top opening length
22.64 m
Compacted surplus or deficit
480.384 m³
Bank borrow needed
0 m³
Download

Working this example

Starting estimate 750.446 m³Bank excavation · BCM

Compare the cut to the installed chamber and stone volume. Only suitable soil can be credited toward the compacted fill target.

See the calculator formulas and assumptions

Questions & answers

How do I include a sloping access ramp for this chamber excavation?

Measure ramp excavation beyond the pit as a separate prismoid or as surveyed end areas.

Does changing the chamber pit’s target fill change spoil truck trips?

The truck estimate assumes all loose cut is hauled. A net export plan must subtract the usable soil kept on site.