Worked example

Cut-to-fill balance for a building pad

A building pad has a defined rectangular cut and a 310 CCY fill target. Its project-specific factors show the residual bank borrow requirement.

Inputs

Measurement system
ft
ft
ft
H:1V
Horizontal run for one unit of vertical rise. Volume geometry only.
%
%
Negative shrink represents compacted expansion relative to bank.
yd³
yd³
PIT SECTION & MATERIAL STATESBattered excavation cross section and bank, loose and compacted volumes. PIT SECTION & MATERIAL STATES 32 ft28 ftDepth 4 ftBANK253.53 yd³LOOSE309.31 yd³COMPACTED215.5 yd³

Estimate

Bank excavation · BCY
253.531 yd³
  • Use site-specific swell and shrink factors. Excavation protection and payload limits require a separate site review.
Loose excavation · LCY
309.308 yd³
Available compacted fill · CCY
215.501 yd³
Loose-volume truck trips
23
Top opening width
32 ft
Top opening length
59 ft
Compacted surplus or deficit
-94.499 yd³
Bank borrow needed
111.175 yd³
Download

Working this example

Starting estimate 253.531 yd³Bank excavation · BCY

For imported material, set a separate bank-to-compacted factor when its density or gradation differs from the site cut.

See the calculator formulas and assumptions

Questions & answers

How is the building-pad compacted fill deficit shown?

The balance equals available compacted cut minus the target compacted fill. A negative balance is the deficit.

Why is bank borrow larger than this pad’s compacted deficit?

At 15% shrink, each bank unit supplies 0.85 compacted units. Divide the compacted deficit by 0.85 to estimate bank borrow of the same material.