Worked example
Cut-to-fill balance for a building pad
A building pad has a defined rectangular cut and a 310 CCY fill target. Its project-specific factors show the residual bank borrow requirement.
Estimate
Bank excavation · BCY
- Use site-specific swell and shrink factors. Excavation protection and payload limits require a separate site review.
- Loose excavation · LCY
- 309.308 yd³
- Available compacted fill · CCY
- 215.501 yd³
- Loose-volume truck trips
- 23
- Top opening width
- 32 ft
- Top opening length
- 59 ft
- Compacted surplus or deficit
- -94.499 yd³
- Bank borrow needed
- 111.175 yd³
Download
Working this example
Starting estimate 253.531 yd³Bank excavation · BCY
For imported material, set a separate bank-to-compacted factor when its density or gradation differs from the site cut.
Questions & answers
How is the building-pad compacted fill deficit shown?
The balance equals available compacted cut minus the target compacted fill. A negative balance is the deficit.
Why is bank borrow larger than this pad’s compacted deficit?
At 15% shrink, each bank unit supplies 0.85 compacted units. Divide the compacted deficit by 0.85 to estimate bank borrow of the same material.