Loam utility trench spoil and truckloads
A utility trench is 120 ft long with a 3 ft bottom and 5 ft depth. Entering the takeoff batter and loam factors estimates spoil, reuse and trips.
Estimate
Bank excavation · BCY
- Use site-specific swell and shrink factors. Excavation protection and payload limits require a separate site review.
- Loose excavation · LCY
- 152.778 yd³
- Available compacted fill · CCY
- 107.556 yd³
- Loose-volume truck trips
- 13
- Top opening width
- 8 ft
- Top opening length
- 120 ft
- Compacted surplus or deficit
- 47.556 yd³
- Bank borrow needed
- 0 yd³
Download
Working this example
Starting estimate 122.222 yd³Bank excavation · BCY
Subtract pipe and bedding displacement from the separate compacted backfill demand. Confirm protection with the field team.
Questions & answers
Does the loam swell factor change the utility trench excavation in place?
Swell changes loose spoil volume. The bank excavation comes from the measured trench geometry.
What dimensions does a square-ended utility trench use for volume?
Use the constant trapezoidal section along the entered bottom length. Add excavated launch or tie-in pits separately.