ConcreteEarthLab

Worked example

Loam utility trench spoil and truckloads

A utility trench is 120 ft long with a 3 ft bottom and 5 ft depth. Entering the takeoff batter and loam factors estimates spoil, reuse and trips.

Inputs

Measurement system
ft
ft
ft
H:1V
Horizontal run for one unit of vertical rise. Volume geometry only.
%
%
Negative shrink represents compacted expansion relative to bank.
yd³
yd³
TRENCH SECTION & MATERIAL STATESBattered excavation cross section and bank, loose and compacted volumes. TRENCH SECTION & MATERIAL STATES 8 ft3 ftDepth 5 ftBANK122.22 yd³LOOSE152.78 yd³COMPACTED107.56 yd³

Estimate

Bank excavation · BCY
122.222 yd³
  • Use site-specific swell and shrink factors. Excavation protection and payload limits require a separate site review.
Loose excavation · LCY
152.778 yd³
Available compacted fill · CCY
107.556 yd³
Loose-volume truck trips
13
Top opening width
8 ft
Top opening length
120 ft
Compacted surplus or deficit
47.556 yd³
Bank borrow needed
0 yd³
Download

Working this example

Starting estimate 122.222 yd³Bank excavation · BCY

Subtract pipe and bedding displacement from the separate compacted backfill demand. Confirm protection with the field team.

See the calculator formulas and assumptions

Questions & answers

Does the loam swell factor change the utility trench excavation in place?

Swell changes loose spoil volume. The bank excavation comes from the measured trench geometry.

What dimensions does a square-ended utility trench use for volume?

Use the constant trapezoidal section along the entered bottom length. Add excavated launch or tie-in pits separately.