DataCenterPUELab

PUE, DCiE, WUE & CUE calculator

Compare facility and IT energy, account for cooling, UPS and lighting overhead, and price a lower PUE target.

Engineering schematic

Facility energy boundary

Live
Facility energy boundary PUE 1.5. DCIE 66.7 %. SITE WUE 1.48 L/kWh. GRID CUE 570 g CO₂e/kWh. See the results table for the full readout. PUE1.5DCIE66.7%SITE WUE1.48L/kWhGRID CUE570g CO₂e/kWh Facility meter13.1k MWhIT equipment8,760 MWhFacility overhead4,380 MWhCurrent overhead / target allowance0%200% usedLimit 100%

Annual energy savings at target 2,190 MWh.

Inputs

Meter readings

Use facility and IT readings from the same boundary and period.

kW
kW
h
Overhead breakdown
kW
kW
kW
Water, carbon & target

For site WUE, include cooling and other water uses within the site boundary.

m³
g/kWh
$/kWh

Calculation details

MeasureValue
Power usage effectiveness1.5
Data center infrastructure efficiency66.67 %
Site water usage effectiveness1.484 L/kWh
Grid carbon usage effectiveness570 g CO₂e/kWh
Annual facility energy13,140 MWh
Annual IT energy8,760 MWh
Total annual facility overhead4,380 MWh
Cooling overhead2,803.2 MWh
UPS & distribution losses963.6 MWh
Lighting overhead175.2 MWh
Other overhead438 MWh
Annual facility energy at target10,950 MWh
Annual energy savings2,190 MWh
Annual energy cost savings240,900 $
Annual grid emissions avoided832.2 t CO₂e

Calculation method

  • PUE = Efacility ÷ EIT
  • DCiE = 100 ÷ PUE
  • Site WUE = site water (L) ÷ IT energy (kWh)
  • Grid CUE = PUE × emissions factor

Enter average kW and operating hours, or enter annual MWh from matching meters. The unassigned portion of facility overhead appears as other overhead. Target savings hold IT energy, tariff and the grid emissions factor constant.

Engineering limits

Use total annual water consumption within the site boundary for site WUE, including cooling and other uses. Grid CUE covers the electricity in the entered facility boundary. Account separately for any on-site fuel or other emissions sources when reporting total operational CUE.

Worked examples