PUE target above the measured baseline
A planning sensitivity uses a higher target PUE than the metered value. Quantify the added facility energy at the same IT load.
Engineering schematic
Facility energy boundary
This target adds 613.2 MWh per year.
Inputs
Calculation details
| Measure | Value |
|---|---|
| Power usage effectiveness | 1.22 |
| Data center infrastructure efficiency | 81.97 % |
| Site water usage effectiveness | 0.822 L/kWh |
| Grid carbon usage effectiveness | 463.6 g CO₂e/kWh |
| Annual facility energy | 10,687.2 MWh |
| Annual IT energy | 8,760 MWh |
| Total annual facility overhead | 1,927.2 MWh |
| Cooling overhead | 1,051.2 MWh |
| UPS & distribution losses | 578.16 MWh |
| Lighting overhead | 175.2 MWh |
| Other overhead | 122.64 MWh |
| Annual facility energy at target | 11,300.4 MWh |
| Annual energy savings | -613.2 MWh |
| Annual energy cost savings | -67,452 $ |
| Annual grid emissions avoided | -233.02 t CO₂e |
Update the highlighted inputs to see the results.
Starting calculation
- Divide 10,687.2 MWh of facility energy by 8,760 MWh of IT energy to get 1.22 PUE.
- At a target PUE of 1.29, facility energy becomes 11,300.4 MWh. The annual difference is -613.2 MWh.
Negative savings mean the scenario spends more energy and money. Reduce the target below the measured PUE to see the sign change.
Calculation method
- PUE = Efacility ÷ EIT
- DCiE = 100 ÷ PUE
- Site WUE = site water (L) ÷ IT energy (kWh)
- Grid CUE = PUE × emissions factor
Enter average kW and operating hours, or enter annual MWh from matching meters. The unassigned portion of facility overhead appears as other overhead. Target savings hold IT energy, tariff and the grid emissions factor constant.
Engineering limits
Use total annual water consumption within the site boundary for site WUE, including cooling and other uses. Grid CUE covers the electricity in the entered facility boundary. Account separately for any on-site fuel or other emissions sources when reporting total operational CUE.
Related worked examples
DataCenterPUELab · Calculation sheet
PUE target above the measured baseline
This target adds 613.2 MWh per year.
Inputs
- Meter basis
- Average power
- Total facility
- 1220 kW
- IT equipment
- 1000 kW
- Annual operating hours
- 8760 h
- Cooling
- 120 kW
- UPS & distribution losses
- 66 kW
- Lighting
- 20 kW
- Annual site water use
- 7200 m³
- Grid emissions factor
- 380 g/kWh
- Energy tariff
- 0.11 $/kWh
- Target PUE
- 1.29
Results
- Power usage effectiveness
- 1.22
- Data center infrastructure efficiency
- 81.97 %
- Site water usage effectiveness
- 0.822 L/kWh
- Grid carbon usage effectiveness
- 463.6 g CO₂e/kWh
- Annual facility energy
- 10,687.2 MWh
- Annual IT energy
- 8,760 MWh
- Total annual facility overhead
- 1,927.2 MWh
- Cooling overhead
- 1,051.2 MWh
- UPS & distribution losses
- 578.16 MWh
- Lighting overhead
- 175.2 MWh
- Other overhead
- 122.64 MWh
- Annual facility energy at target
- 11,300.4 MWh
- Annual energy savings
- -613.2 MWh
- Annual energy cost savings
- -67,452 $
- Annual grid emissions avoided
- -233.02 t CO₂e
Screening estimate. Confirm against facility and manufacturer data for engineering decisions.