Stranded power under a design cap
A conservative 65% utilization cap constrains how much installed capacity is usable for the IT load.
Engineering schematic
A/B capacity topology
Usable IT headroom 26.4 kW
Inputs
Calculation details
| Measure | Value |
|---|---|
| Real rating per module | 376 kW |
| Installed rating per path | 2,256 kW |
| Total installed nameplate | 4,512 kW |
| Protected capacity before design cap | 2,256 kW |
| Capacity on a path with one module removed | 1,880 kW |
| Surviving capacity with one full path isolated | 2,256 kW |
| Maintenance ceiling with standby reserve held | 2,256 kW |
| Usable IT at design cap | 1,466.4 kW |
| Usable capacity assigned to planned load | 1,440 kW |
| Capacity allocated to redundancy | 2,256 kW |
| Capacity withheld by utilization cap | 789.6 kW |
| Unassigned usable capacity | 26.4 kW |
| Usable IT headroom against plan | 26.4 kW |
| Usable share of installed nameplate | 32.5 % |
| Installed module capex | 816,000 $ |
| Module capex per usable IT kW | 556 $/kW |
Update the highlighted inputs to see the results.
Starting calculation
- Each 400 kVA module at 0.94 power factor supplies 376 kW. Holding the topology reserve leaves 2,256 kW protected.
- Apply the 65% design cap to get 1,466.4 kW usable. The planned load leaves 26.4 kW of headroom.
The unused capacity withheld by the cap is distinct from the idle capacity available within the cap.
Calculation method
- Module kW = module kVA × rated power factor
- Protected kW = (modules per path − spare modules) × module kW
- Design IT limit = protected kW × utilization cap
Dual paths are equal in size and either path can carry the modeled load. The path-isolated ceiling keeps the specified module reserve on the surviving path. Usable capacity is split into assigned load and idle headroom. Stranded kW is the amount withheld by the design cap.
Engineering limits
A single-path design has zero capacity through an isolated path. Module redundancy alone cannot establish a Tier classification. Concurrent maintainability also depends on the physical distribution, isolation, component arrangements and maintenance procedures.
Related worked examples
DataCenterPUELab · Calculation sheet
Stranded power under a design cap
Usable IT headroom 26.4 kW
Inputs
- Redundancy scheme
- 2N
- Modules per path
- 6
- Rating per module
- 400 kVA
- Rated power factor
- 0.94
- Design utilization cap
- 65 %
- Planned IT load
- 1440 kW
- Installed cost per module
- 68000 $
Results
- Real rating per module
- 376 kW
- Installed rating per path
- 2,256 kW
- Total installed nameplate
- 4,512 kW
- Protected capacity before design cap
- 2,256 kW
- Capacity on a path with one module removed
- 1,880 kW
- Surviving capacity with one full path isolated
- 2,256 kW
- Maintenance ceiling with standby reserve held
- 2,256 kW
- Usable IT at design cap
- 1,466.4 kW
- Usable capacity assigned to planned load
- 1,440 kW
- Capacity allocated to redundancy
- 2,256 kW
- Capacity withheld by utilization cap
- 789.6 kW
- Unassigned usable capacity
- 26.4 kW
- Usable IT headroom against plan
- 26.4 kW
- Usable share of installed nameplate
- 32.5 %
- Installed module capex
- 816,000 $
- Module capex per usable IT kW
- 556 $/kW
Screening estimate. Confirm against facility and manufacturer data for engineering decisions.