Radiant Floor GPM at 10°F vs. 20°F ΔT

Compare total and per-loop radiant flow for 34,000 BTU/h at a 10°F or 20°F supply-to-return temperature drop.

Heated surface and tubing

Subtract walls, fixed cabinets and other areas without active tube.

Adds footage for turns and layout variation.

Manifold and heat load

Enter the one-way distance. The model adds supply and return tails.

Includes both tails. Use a lower limit when the hydraulic design calls for it.

Results

Example estimate
Total tubing including tails2,044 ft
SupplyReturn 272 ft active per loop
One circuit shown. Supply and return tails are included in the balanced loop length.
Balanced loop length
292 ft
Balanced circuits
7 loops
Manifold supply/return pairs
7 ports
Active tubing before tails
1,904 ft
Supply and return tails per loop
20 ft
Design floor load
34,000 BTU/h
Total manifold flow
6.8 GPM
Flow per loop
0.97 GPM
Modeled tubing velocity
1.76 ft/s
Tubing and assumed ID
PEX-A · 0.475 in ID
  • Verify tubing ID, bend radius, oxygen barrier, floor output and pump head for the installed system.

Worked example

The floor has a 34,000 BTU/h design load. At 10°F drop it needs 6.8 GPM of water. At 20°F the same load requires about 3.4 GPM, while the circuit count stays tied to geometry.

Total tubing including tails 2,044 ft

What to check next

Verify supply water temperature, surface temperature and allowable across-floor temperature difference with the selected assembly. Pump selection also needs the critical loop’s head loss.

Formulas and assumptions

Active tube
Active footage = floor area × 12 ÷ spacing in inches × (1 + routing allowance).
Balanced circuits
Circuit count = round up(active footage ÷ (loop limit − two manifold tails)). Balanced length = active footage ÷ circuits + tails.
Water flow
GPM = BTU/h ÷ (500 × supply-return ΔT). Divide system flow by the number of equally loaded circuits. The velocity uses representative tubing ID.

Frequently asked questions

Does a larger hydronic ΔT reduce per-loop GPM by the same proportion?

With the same water and load, doubling ΔT halves total flow and each balanced loop’s share. Check floor output and comfort at the new operating temperatures.

Why does the radiant calculator use 500 in the water flow formula?

The rounded constant combines water density, specific heat and 60 minutes per hour. Glycol mixtures require a different fluid factor.