Radiant Floor PEX Tubing Length Calculator

Estimate ½-inch or ⅝-inch PEX footage, balanced circuits, manifold ports and flow for hydronic radiant floors at 6 to 12 inches on center.

Heated surface and tubing

Subtract walls, fixed cabinets and other areas without active tube.

Adds footage for turns and layout variation.

Manifold and heat load

Enter the one-way distance. The model adds supply and return tails.

Includes both tails. Use a lower limit when the hydraulic design calls for it.

Results

Example estimate
Total tubing including tails1,544 ft
SupplyReturn 233.3 ft active per loop
One circuit shown. Supply and return tails are included in the balanced loop length.
Balanced loop length
257.3 ft
Balanced circuits
6 loops
Manifold supply/return pairs
6 ports
Active tubing before tails
1,400 ft
Supply and return tails per loop
24 ft
Design floor load
22,000 BTU/h
Total manifold flow
2.93 GPM
Flow per loop
0.49 GPM
Modeled tubing velocity
0.89 ft/s
Tubing and assumed ID
PEX-A · 0.475 in ID
  • Verify tubing ID, bend radius, oxygen barrier, floor output and pump head for the installed system.

Worked example

Lay out 1,000 heated ft² at 9 inches on center and add 12 ft from the manifold in each direction. The loop count must leave room for both tails within the selected total length.

Total tubing including tails 1,544 ft

Formulas and assumptions

Active tube
Active footage = floor area × 12 ÷ spacing in inches × (1 + routing allowance).
Balanced circuits
Circuit count = round up(active footage ÷ (loop limit − two manifold tails)). Balanced length = active footage ÷ circuits + tails.
Water flow
GPM = BTU/h ÷ (500 × supply-return ΔT). Divide system flow by the number of equally loaded circuits. The velocity uses representative tubing ID.

Frequently asked questions

Does the 300-foot example include both radiant manifold leads?

Yes. Circuit length includes the active serpentine and the full supply and return route between the floor and manifold.

Can I use a single spacing for every radiant floor zone?

Use a layout and output calculation that accounts for floor covering, perimeter losses and water temperature. Zones with different loads can need different spacing.

Does changing from PEX-A to PEX-B change estimated footage?

The geometric footage calculation uses area, spacing and routing. Confirm the selected product’s inside diameter, bend radius and oxygen barrier for hydraulic and installation design.