750 PPFD for 12 hours on a fruiting canopy

A 16 ft² fruiting canopy is planned for 750 µmol/m²/s over 12 hours. The proposed LED delivers 2.7 µmol/J at 90% assumed capture.

Inputs

Daily light
µmol/m²/s
h/day
mol/m²/day

Leave at zero for a room lit only by lamps.

Coverage and operating cost
ft²
µmol/J
%
W
USD/kWh
days

Results

Total daily light integral

32.4 mol/m²/day

Fruiting canopy · 25–35 mol/m²/day planning band

Lamp contribution
32.4 mol/m²/day
Estimated target power
458.8 W
Coverage per fixture at target PPFD
17.44 ft²
Whole fixtures at rated power
1
Target-power energy
165.16 kWh/month
Target-power electricity cost
41.29 USD/month
Whole-fixture electricity cost
45 USD/month

Crop target gauge

Illustrative range. Set a crop-specific target before choosing fixtures.

Daily light target gauge32.4 mol per square meter per day. Illustrative band: Fruiting canopy 25–35DLI · mol/m²/day32.4044Fruiting canopy 25–35

Worked calculation

  1. Integrate lamp PPFD over the photoperiod

    750 × 12 × 0.0036 = 32.4 mol/m²/day

  2. Add measured sunlight contribution

    32.4 + 0 = 32.4 mol/m²/day

  3. Convert canopy photon demand into wall power

    750 × 1.4864 m² ÷ (2.7 × 0.9) = 458.78 W

  4. Find area per fixture at target PPFD

    500 × 2.7 × 0.9 ÷ 750 = 17.44 ft²

  5. Price the scheduled energy

    0.45878 kW × 12 h × 30 days × $0.25 = $41.29 per month at target power

What the example shows

The resulting DLI is 32.4 mol/m²/day. This example needs about 459 W at target output. Compare the predicted light dose with the specific cultivar and production stage.

How the model works

The 0.0036 factor converts micromoles per second over an hour into moles per day. Use average canopy PPFD for an even lamp schedule. For variable daylight, record the sunlight DLI separately and add it once.

Photon efficacy describes fixture output per watt of electrical input. The canopy capture percentage models optical and edge losses. Mounting height, dimming, spacing and reflection affect the delivered PPFD. Check a fixture map or measure several locations across the canopy.

References

Common questions

What if a fruiting canopy gets less PPFD below the upper leaves?

Record measurements at the heights relevant to your crop. The top-canopy DLI is a point-of-reference and does not describe the light in shaded layers.

Does a 12-hour day automatically suit every fruiting variety?

Photoperiod response depends on the species and cultivar. Treat the hours as a lighting schedule input and follow crop-specific guidance on day length.