230 V input with 20 ms hold-up

Check a 270 µF capacitor for a 135 W supply on a 50 Hz bridge bus.

Design inputs

Mains & bridge
Bus requirements

Enter 0 to use the governing capacitance.

View live readout ↑

Live readout

Edit inputs
Bulk cap
210 µF
Bus valley
256.1 V
Bus ripple
18.49 V
Hold-up
28.22 ms
Bulk capacitor bus Bulk capacitor bus 50 Hz mains VbusRipple cycleMains outageLow-line pk275 VBus floor185 VHold-up28.2 ms
The outage begins at the settled low-line valley. The bus voltage drops as stored capacitor energy supplies a constant load.
Bus design headroom available

Voltage headroom includes the entered surge allowance. Check inrush, capacitor tolerance and ripple-current rating separately.

Bus stress / voltage rating355.9 V / 450 V

Bus ripple / goal18.49 V / 24 V

Required / available hold-up20 ms / 28.22 ms

Result breakdown
Low-line input195.5 V RMS
Low-line rectified peak274.579 V
Nominal rectified peak323.369 V
High-line rectified peak355.896 V
High-line stress with surge allowance355.896 V
Constant power from bus150 W
Valley at ripple target250.579 V
Estimated operating valley256.092 V
Estimated peak-to-peak ripple18.4868 V
Discharge interval at ripple target8.66392 ms
Capacitance for ripple206.222 µF
Capacitance for hold-up210.049 µF
Governing capacitance210.049 µF
Governing requirementHold-up
Capacitance used in readout270 µF
Estimated hold-up from valley28.2223 ms
Hold-up headroom8.22226 ms
Bus ripple headroom5.51316 V
High-line voltage headroom94.104 V

Worked calculation

Cbulk = max(206.222 µF for ripple, 210.049 µF for hold-up) = 210.049 µF

Compare required ripple and hold-up capacitances before checking the operating valley and the DC voltage margin.

Rectified peaks

Vpk,min = √2 · Vac,min − n · Vf | n = 2 (bridge), 1 (half wave)

Full-wave recharge events occur twice per mains cycle. Half-wave recharge occurs once. Under the ideal source model, recharge begins when the rising rectified sine crosses the falling bus.

Ripple & outage energy

Cripple = 2·Pin·tdis/(Vpk,min² − Vvalley²) | Chold = 2·Pin·thold/(Vvalley² − Vmin²)

Vvalley is the low-line peak minus target ripple. Sizing hold-up from that target valley is conservative. For the selected capacitance, the readout solves the modeled crossing and calculates available hold-up from its operating valley.

Hardware checks

Vheadroom = Vrated − (Vpk,high + Vsurge)

This margin covers the steady high-line crest plus the entered surge allowance. Verify surge waveform, ripple-current rating, tolerance and useful life against the actual capacitor. A real bridge requires inrush limiting, source-impedance and charge-pulse checks.