Bulk capacitor with inadequate high-line rating

A 350 V capacitor is available for a nominal 230 V mains design.

Design inputs

Mains & bridge
Bus requirements

Enter 0 to use the governing capacitance.

View live readout ↑

Live readout

Edit inputs
Bulk cap
114.6 µF
Bus valley
273.7 V
Bus ripple
10.62 V
Hold-up
68.21 ms
Bulk capacitor bus Bulk capacitor bus 50 Hz mains VbusRipple cycleMains outageLow-line pk284 VBus floor175 VHold-up68.2 ms
The outage begins at the settled low-line valley. The bus voltage drops as stored capacitor energy supplies a constant load.
Bus design limit exceeded

Voltage headroom includes the entered surge allowance. Check inrush, capacitor tolerance and ripple-current rating separately.

Bus stress / voltage rating362.4 V / 350 V

Bus ripple / goal10.62 V / 20 V

Required / available hold-up17 ms / 68.21 ms

Result breakdown
Low-line input202.4 V RMS
Low-line rectified peak284.337 V
Nominal rectified peak323.369 V
High-line rectified peak362.401 V
High-line stress with surge allowance362.401 V
Constant power from bus71.4286 W
Valley at ripple target264.337 V
Estimated operating valley273.713 V
Estimated peak-to-peak ripple10.6238 V
Discharge interval at ripple target8.80304 ms
Capacitance for ripple114.602 µF
Capacitance for hold-up61.8761 µF
Governing capacitance114.602 µF
Governing requirementRipple
Capacitance used in readout220 µF
Estimated hold-up from valley68.2125 ms
Hold-up headroom51.2125 ms
Bus ripple headroom9.37621 V
High-line voltage headroom-12.4014 V

Worked calculation

Cbulk = max(114.602 µF for ripple, 61.8761 µF for hold-up) = 114.602 µF

Check the high-line DC voltage headroom even when the installed capacitance meets the hold-up time.

Rectified peaks

Vpk,min = √2 · Vac,min − n · Vf | n = 2 (bridge), 1 (half wave)

Full-wave recharge events occur twice per mains cycle. Half-wave recharge occurs once. Under the ideal source model, recharge begins when the rising rectified sine crosses the falling bus.

Ripple & outage energy

Cripple = 2·Pin·tdis/(Vpk,min² − Vvalley²) | Chold = 2·Pin·thold/(Vvalley² − Vmin²)

Vvalley is the low-line peak minus target ripple. Sizing hold-up from that target valley is conservative. For the selected capacitance, the readout solves the modeled crossing and calculates available hold-up from its operating valley.

Hardware checks

Vheadroom = Vrated − (Vpk,high + Vsurge)

This margin covers the steady high-line crest plus the entered surge allowance. Verify surge waveform, ripple-current rating, tolerance and useful life against the actual capacitor. A real bridge requires inrush limiting, source-impedance and charge-pulse checks.