An edge compute hall operates 6,300 hours per year at the entered average load. Its overhead is measured over those same operating hours.

Engineering schematic

Facility energy boundary

Live
Facility energy boundary PUE 1.567. DCIE 63.8 %. SITE WUE 0.34 L/kWh. GRID CUE 596 g CO₂e/kWh. See the results table for the full readout. PUE1.567DCIE63.8%SITE WUE0.34L/kWhGRID CUE596g CO₂e/kWh Facility meter1,323 MWhIT equipment844.2 MWhFacility overhead478.8 MWhCurrent overhead / target allowance0%132% usedLimit 100%

Annual energy savings at target 115.8 MWh.

Inputs

Meter readings

Use facility and IT readings from the same boundary and period.

kW
kW
h
Overhead breakdown
kW
kW
kW
Water, carbon & target

For site WUE, include cooling and other water uses within the site boundary.

m³
g/kWh
$/kWh

Calculation details

MeasureValue
Power usage effectiveness1.567
Data center infrastructure efficiency63.81 %
Site water usage effectiveness0.344 L/kWh
Grid carbon usage effectiveness595.52 g CO₂e/kWh
Annual facility energy1,323 MWh
Annual IT energy844.2 MWh
Total annual facility overhead478.8 MWh
Cooling overhead283.5 MWh
UPS & distribution losses113.4 MWh
Lighting overhead37.8 MWh
Other overhead44.1 MWh
Annual facility energy at target1,207.21 MWh
Annual energy savings115.79 MWh
Annual energy cost savings22,001 $
Annual grid emissions avoided44 t CO₂e

Starting calculation

  1. Divide 1,323 MWh of facility energy by 844.2 MWh of IT energy to get 1.567 PUE.
  2. At a target PUE of 1.43, facility energy becomes 1,207.21 MWh. The annual difference is 115.79 MWh.

Switch to annual energy to see the equivalent readings. The PUE stays constant through the change in basis.

Calculation method

  • PUE = Efacility ÷ EIT
  • DCiE = 100 ÷ PUE
  • Site WUE = site water (L) ÷ IT energy (kWh)
  • Grid CUE = PUE × emissions factor

Enter average kW and operating hours, or enter annual MWh from matching meters. The unassigned portion of facility overhead appears as other overhead. Target savings hold IT energy, tariff and the grid emissions factor constant.

Engineering limits

Use total annual water consumption within the site boundary for site WUE, including cooling and other uses. Grid CUE covers the electricity in the entered facility boundary. Account separately for any on-site fuel or other emissions sources when reporting total operational CUE.

Related worked examples