Seasonal edge-site annualization
An edge compute hall operates 6,300 hours per year at the entered average load. Its overhead is measured over those same operating hours.
Engineering schematic
Facility energy boundary
Annual energy savings at target 115.8 MWh.
Inputs
Calculation details
| Measure | Value |
|---|---|
| Power usage effectiveness | 1.567 |
| Data center infrastructure efficiency | 63.81 % |
| Site water usage effectiveness | 0.344 L/kWh |
| Grid carbon usage effectiveness | 595.52 g CO₂e/kWh |
| Annual facility energy | 1,323 MWh |
| Annual IT energy | 844.2 MWh |
| Total annual facility overhead | 478.8 MWh |
| Cooling overhead | 283.5 MWh |
| UPS & distribution losses | 113.4 MWh |
| Lighting overhead | 37.8 MWh |
| Other overhead | 44.1 MWh |
| Annual facility energy at target | 1,207.21 MWh |
| Annual energy savings | 115.79 MWh |
| Annual energy cost savings | 22,001 $ |
| Annual grid emissions avoided | 44 t CO₂e |
Update the highlighted inputs to see the results.
Starting calculation
- Divide 1,323 MWh of facility energy by 844.2 MWh of IT energy to get 1.567 PUE.
- At a target PUE of 1.43, facility energy becomes 1,207.21 MWh. The annual difference is 115.79 MWh.
Switch to annual energy to see the equivalent readings. The PUE stays constant through the change in basis.
Calculation method
- PUE = Efacility ÷ EIT
- DCiE = 100 ÷ PUE
- Site WUE = site water (L) ÷ IT energy (kWh)
- Grid CUE = PUE × emissions factor
Enter average kW and operating hours, or enter annual MWh from matching meters. The unassigned portion of facility overhead appears as other overhead. Target savings hold IT energy, tariff and the grid emissions factor constant.
Engineering limits
Use total annual water consumption within the site boundary for site WUE, including cooling and other uses. Grid CUE covers the electricity in the entered facility boundary. Account separately for any on-site fuel or other emissions sources when reporting total operational CUE.
Related worked examples
DataCenterPUELab · Calculation sheet
Seasonal edge-site annualization
Annual energy savings at target 115.8 MWh.
Inputs
- Meter basis
- Average power
- Total facility
- 210 kW
- IT equipment
- 134 kW
- Annual operating hours
- 6300 h
- Cooling
- 45 kW
- UPS & distribution losses
- 18 kW
- Lighting
- 6 kW
- Annual site water use
- 290 m³
- Grid emissions factor
- 380 g/kWh
- Energy tariff
- 0.19 $/kWh
- Target PUE
- 1.43
Results
- Power usage effectiveness
- 1.567
- Data center infrastructure efficiency
- 63.81 %
- Site water usage effectiveness
- 0.344 L/kWh
- Grid carbon usage effectiveness
- 595.52 g CO₂e/kWh
- Annual facility energy
- 1,323 MWh
- Annual IT energy
- 844.2 MWh
- Total annual facility overhead
- 478.8 MWh
- Cooling overhead
- 283.5 MWh
- UPS & distribution losses
- 113.4 MWh
- Lighting overhead
- 37.8 MWh
- Other overhead
- 44.1 MWh
- Annual facility energy at target
- 1,207.21 MWh
- Annual energy savings
- 115.79 MWh
- Annual energy cost savings
- 22,001 $
- Annual grid emissions avoided
- 44 t CO₂e
Screening estimate. Confirm against facility and manufacturer data for engineering decisions.