Pump suction

Flooded-Suction NPSH from a Vented Reservoir

Check NPSH for a 60 gpm pump with the reservoir water level 6 ft above its centerline.

Inputs

NPSH available38.12 ft

Site and suction duty

gpm
°F
ft
ftUse the low operating water level relative to the pump centerline.
ftRead at actual flow and speed on the pump curve.
ft

Suction pipe and fittings

ftMeasure along the pipe, including vertical runs.
K = 0.9 each for this estimate.
K = 2.5 each for this estimate.
Sum the K values for other fittings.
inEnter 0 to use the nominal-size table.
inEnter 0 to use the material preset.
Surface pressure
psiaEnter 0 to use the elevation estimate.
psigEnter 0 for a vessel vented to atmosphere.

Results

Updates as you edit
NPSH available38.12 ft

Available NPSH meets the entered margin at this duty point.

Available NPSH versus flow
Available NPSH versus flowThe horizontal references hold the duty-point NPSHr and margin fixed. Read NPSHr at each flow for a full curve check.01836547290010.7521.4932.2442.98Suction flow (gpm)NPSH (ft)Entered duty · 38.12 ft
  • Available NPSH
  • Entered NPSHr
  • Required + margin

The horizontal references hold the duty-point NPSHr and margin fixed. Read NPSHr at each flow for a full curve check.

Margin above NPSH required
26.12 ft
NPSH required with target margin
16 ft
Available ÷ required
3.18
Site atmospheric pressure
14.7 psia
Water vapor pressure
0.389 psia
Vapor pressure head
0.9 ft
Suction pipe and fitting loss
0.96 ft
Maximum lift at target margin
16.12 ft

Worked calculation

  1. Set the pressure at the liquid surface

    Surface pressure = site atmospheric pressure + vessel gauge pressure

    The site pressure is 14.7 psia and the liquid surface is at 14.7 psia, equivalent to 33.97 ft of head.

  2. Find water vapor pressure

    IAPWS saturation relation: ln(pᵥ/p𝒸) = (T𝒸/T) × Σaᵢ(1 − T/T𝒸)ᵖⁱ

    72 °F water has 0.389 psia of vapor pressure, or 0.9 ft of head.

  3. Account for liquid level and suction losses

    NPSHa = surface head + signed liquid level − vapor head − suction loss

    33.97 ft + (6 ft) − 0.9 ft − 0.96 ft = 38.12 ft.

  4. Compare with the pump and margin target

    Available margin = NPSHa − NPSHr

    The available margin is 26.12 ft. The entered NPSHr and margin call for 16 ft total.

What this example shows

Positive liquid level contributes head. Use the reservoir’s lowest operating water surface for a conservative flooded-suction check.

Frequently asked questions

Why does flooded suction add the reservoir level to NPSH?

The water surface sits above the pump, so elevation increases inlet head before pipe losses.

Does a flooded reservoir guarantee enough NPSH at all flows?

Losses increase with flow and the pump’s required NPSH can also change. Check the full expected operating range.