Drip Lateral Pressure Drop on an Uphill Run
Assess a 210 ft drip lateral that rises 12 ft, with a 20 psi inlet and 12 psi minimum emitter pressure.
Inputs
Results
Updates as you editThe entered pressure budget and 5 ft/s velocity screen are met.
- Calculated pressure
- Minimum outlet pressure
Flow drops at each outlet. The pressure model keeps each outlet at its rated flow.
- Gross precipitation rate
- 0.27 in/h
- Weekly run time
- 250.8 min
- Mainline velocity
- 2.6 ft/s
- Critical lateral inlet velocity
- 2.45 ft/s
- Critical lateral inlet flow
- 1.75 gpm
- Outlets on critical lateral
- 140
- Lateral friction drop
- 1.78 psi
- Lowest lateral pressure
- 13.03 psig
- Estimated maximum drip run
- 229.5 ft
Inputs
- Emitter type
- Inline drip
- Parallel drip laterals
- 4
- Drip lateral length
- 210 ft
- Emitter spacing
- 18 in
- Lateral row spacing
- 3 ft
- Flow per drip emitter
- 0.75 gal/h
- Mainline inside diameter
- 1.049 in
- Lateral inside diameter
- 0.54 in
- Net weekly water depth
- 0.95 in
- Application efficiency
- 85 %
- Pressure at lateral entrance
- 20 psig
- Minimum outlet pressure
- 12 psig
- Elevation change along run
- 12 ft
- Lateral Hazen–Williams C
- 150
Worked calculation
Count outlets and total the flow
Emitters per line = floor(run length / spacing). Zone flow = total emitters × flow per emitter.
560 outlets give 7 gpm over 2,520 ft².
Turn flow into application rate
Gross depth per hour = hourly zone volume / wetted area
The gross rate is 0.27 in/h and the net target is 0.95 in per week at 85 % efficiency.
Calculate the weekly run time
Minutes per week = 60 × target depth / (gross hourly rate × efficiency)
The weekly runtime is 250.8 min.
Track pressure down the lateral
Each segment carries the flow for its remaining outlets. Segment head loss uses Hazen–Williams.
Friction contributes 1.78 psi. Adding elevation gives a lowest gauge pressure of 13.03 psig. At the same slope, the pressure and velocity limits allow about 229.5 ft.
What this example shows
The uphill rise consumes part of the pressure budget before accounting for friction. Try shorter laterals at the same slope or compare a larger bore.
Frequently asked questions
How does a 12 ft uphill rise use pressure on the dripline?
It costs about 5.2 psi of water pressure head. The friction losses add to that elevation cost.
How do I compare a shorter run on the same uphill grade?
Scale the entered rise along with the length. The max-run result already holds the entered slope constant.