Well Pressure Tank Drawdown & Pre-Charge Calculator
Use Boyle’s law to estimate usable drawdown, refill time and minimum tank size for a given pump and switch.
Inputs
Results
Updates as you editThe no-demand refill is shorter than the entered minimum pump run time.
- Water in tank
The two switch points enclose the usable drawdown. Air compression is modeled as isothermal.
- Minimum nominal tank volume
- 116.3 gal
- Shortest run time (no demand)
- 1.48 min
- Refill time at entered demand
- 2.02 min
- Pump-off time at entered demand
- 5.55 min
- Usable acceptance fraction
- 25.8 %
- Recommended drained pre-charge
- 38 psig
- Drawdown for run time target
- 30 gal
- Water in tank at cut-out
- 25.33 gal
Inputs
- Pressure switch
- 40 / 60 psi
- Nominal tank volume
- 86 gal
- Pump delivery at tank
- 15 gpm
- Demand while cycling
- 4 gpm
- Minimum pump run time
- 2 min
- Pre-charge setting
- 2 psi below cut-in
- Site elevation
- 0 ft
Worked calculation
Convert gauge pressure to absolute pressure
Pabs = gauge pressure + local atmospheric pressure
The cut-in, cut-out and pre-charge are 54.7 psia, 74.7 psia, 52.7 psia on an absolute basis.
Compute the water fraction at both switch points
Boyle’s law: P₀V₀ = PVair. Water fraction = max(0, 1 − P₀/P).
The water fraction increases from 3.66 % to 29.45 %, a gain of 25.8 %.
Multiply by the nominal tank volume
Drawdown = nominal tank volume × change in water fraction
86 gal × 25.8 % gives 22.18 gal of usable water.
Check run time and size the tank
Shortest refill = drawdown / pump flow. Minimum tank = pump flow × run time / usable fraction.
15 gpm over 2 min requires 30 gal of drawdown. That corresponds to 116.3 gal of nominal tank volume.
Model and assumptions
Use absolute air pressure
The model adds local atmospheric pressure to each gauge value and uses Boyle’s law with an ideal isothermal air chamber. Actual usable volume varies with diaphragm geometry and manufacturer acceptance limits.
Check the shortest refill
With all outlets closed the tank receives the full pump flow. Use the motor’s minimum run time, often one or two minutes for the examples here. Set drained pre-charge according to the tank instructions.
Engineering references
Frequently asked questions
How is pressure tank drawdown different from maximum acceptance?
Drawdown is the water delivered between two switch points. Maximum acceptance is the most water the particular vessel can hold under its design conditions.
Why name the shortest and flowing refill times separately?
No-demand refill uses the entire pump flow. Competing demand leaves less flow to fill the tank, which lengthens refill or prevents cut-out.