Well and transfer pumps

Pump Head Through 800 ft of Schedule 80 PVC

See how a 1½-inch Schedule 80 line affects an 18 gpm spring-to-tank transfer with 73 ft of static lift.

Inputs

Total dynamic head96.86 ft

Duty point

gpm
ftWater level below the wellhead with the pump off.
ftAdditional drop in water level at the target flow.
ftUse a negative value for a lower outlet.
psigEnter 0 for an open tank.
ftMeasure along the pipe, including vertical runs.
Fittings and friction method
°F
K = 0.9 each for this estimate.
K = 2.5 each for this estimate.
Sum the K values for other fittings.
inEnter 0 to use the nominal-size table.
Enter 0 to use the material preset.
inEnter 0 to use the material preset.
Candidate pump curve
ft
gpm
ftUse a published point at the chosen speed.

Results

Updates as you edit
Total dynamic head96.86 ft

The candidate curve has sufficient head at the target flow.

Pump and system curves
Pump and system curvesThe two-point pump curve is an interpolation. The system curve holds the entered pumping water level fixed.0714212835044.5589.1133.65178.2Flow (gpm)Head (ft)Target duty · 96.86 ftIntersection · 117.76 ft
  • System curve
  • Entered pump curve

The two-point pump curve is an interpolation. The system curve holds the entered pumping water level fixed.

Static elevation lift
73 ft
Outlet pressure head
0 ft
Darcy straight-pipe loss
23.65 ft
Hazen–Williams straight-pipe loss
22.85 ft
Fitting loss
1.01 ft
Pipe velocity
3.27 ft/s
Pipe inside diameter
1.5 in
Candidate head at target
139.52 ft
Estimated intersection flow
25.25 gpm
Estimated intersection head
117.76 ft

Worked calculation

  1. Find the pumping water level

    Pumping depth = static depth + drawdown

    30 ft + 5 ft = 35 ft below the wellhead. The outlet then gives 73 ft of static lift.

  2. Convert delivery pressure to head

    Hₚ = p / (ρg)

    0 psig gives 0 ft of pressure head at the entered water temperature.

  3. Add pipe and fitting losses

    H𝒻 = f(L/D) v²/(2g) or 10.67 L(Q/C)¹·⁸⁵² / D⁴·⁸⁷⁰⁴ in SI. Hₖ = ΣK v²/(2g).

    At 18 gpm the selected method adds 22.85 ft and fittings add 1.01 ft.

  4. Build the duty point

    TDH = static lift + pressure head + straight-pipe loss + fittings

    73 ft + 0 ft + 22.85 ft + 1.01 ft = 96.86 ft.

  5. Compare with the candidate pump

    H(Q) = H₀ − (H₀ − H₁)(Q/Q₁)²

    The candidate develops 139.52 ft at 18 gpm, a head difference of 42.66 ft.

What this example shows

Change the material to Schedule 40 while keeping nominal size and flow steady. The wider bore reduces straight-pipe loss. Check pressure and temperature rating separately when selecting pipe.

Frequently asked questions

Why does Schedule 80 add head at equal flow?

Its thicker wall reduces the inside diameter at a given nominal size, which raises velocity and friction.

Can the long spring transfer use a surveyed straight-line distance?

Measure the developed pipe run along hills, offsets and the vertical sections. Use the elevation difference separately.